handshake Home | Status quo for construction of contracts

Status quo for construction of contracts

13 August 2009

A House of Lords case has reaffirmed the principles courts will apply when interpreting a contract.

It has also reiterated the long-standing rule that evidence of pre-contractual negotiations is not admissible to assist with contractual interpretation – the exclusionary rule.

The case serves as a useful reminder of the importance of ensuring contract terms are clearly understood and precisely drafted.

The case concerned a dispute between a landowner and property developer over the correct interpretation of a term in the parties’ development agreement.

The agreement contained a formula for calculating an additional sum payable to the landowner. The parties disagreed over the construction of the formula to the tune of more than £3.5 million, and so went to court to resolve their differences.

The House of Lords confirmed that an objective approach must be taken when interpreting contractual terms. What would a reasonable person – having all background information available to the parties at the time of the contract – have understood the parties to have meant by the language they used?

Taking into account the background and context of this particular agreement (but not the parties’ pre-contractual negotiations), the court concluded that something had clearly gone wrong with the language and drafting, and it was clear what a reasonable person would have understood the parties to have meant.

For the court to have interpreted the disputed term along the ordinary rules of syntax would have made no commercial sense, and so substituted its own construction of the contract.

Although the case was decided upon the basis of construction, the House of Lords did go on to consider issues raised in relation to the admissibility of pre-contractual negotiations.

The court confirmed that there was still no good reason to depart from the exclusionary rule in determining disputes regarding the construction of contracts.

However, it pointed out that pre-contractual negotiations could be potentially relevant as part of the factual background, which might cast light on what was meant by the language used. Whilst the court acknowledged that pre-contractual negotiations may be admissible only in ‘exceptional cases’, the line between facts and pre-contractual negotiations has arguably been blurred.

What does this mean?

What should you do?

Chartbrook Limited v Persimmon Homes Limited

© Shoosmiths. This page is for general information: it is not legal advice. Please read our full terms and conditions for details of the disclaimers and exclusions which apply.

Get in touch

Jon Bartley

Partner
T: 03700 86 8730
I: +44 (0)118 965 8730
E: jonathan.bartley@shoosmiths.co.uk